Day 47 of the house remodel, it be 12:30 pm, so it is update time. Lots of plumbing work completed, the counter template has been built and the sink is installed. The pictures show what the cabinets look like at noon and how the sun shines through the bay window over the sink.
Since next week is a short week due to Thanksgiving, we are not expecting much progress next week. Tony indicates that he will be working on the under cabinet electrical outlets and the rafters, while we wait for the counter top to be cut. For Cinna and I, we need to pick a final color for the kitchen and find two hanging lights. Other than that progress is still on time and on budget.
A couple of pic looking into the laundry / 1/2 bath area and one shot looking out from the laundy area.